Two houses, same 3,000 feet. One has 1,000 of it below grade. The appraiser doesn't call that one 3,000. The below-grade part sits on its own line and the comps discount it. Cheaper per foot to build, and it reads as less house at the refi.
1
25
GLA is above grade only. If any part of the level sits below surrounding grade, the whole level usually goes below grade, walkout or not. Two recent comps will tell you what the below-grade adjustment runs locally. On a flat lot it's often small enough not to matter.
2
The appraisal is good 90 to 120 days. The DSCR cash-out wants six months of seasoning. Order the appraisal early and it expires before you're eligible. The fix is a recert, and a recert can come back lower. Count backward from the seasoning date.
1
1
1
39
Lenders differ on where seasoning starts. Some run it from the deed date, some from the date the last rehab draw closed. Worth settling that with the lender before you order anything. It moves the appraisal date by weeks.
19
Your owner's title policy excepts anything an accurate survey would show. The neighbor's drive over your corner. A utility line across the back. Not covered unless you order the survey and have the exception deleted. You find out the day you go to build.
1
1
2
92
The timing is the inspection period. Order it then, and get it to title before closing. Ask to have the survey exception deleted. Sometimes they will. Sometimes they swap it for one naming what the survey actually found, which still beats a blanket exception.
1
19
Electric and gas go in the tenant's name. In a lot of cities water and sewer can't. The account stays with the house. An unpaid balance rides on the property long after that tenant is gone. You find out at the next closing, when title makes you clear it.
2
4
89
Where the utility allows it, put water in the tenant's name. Where it doesn't, bill it back monthly instead of letting it ride to turnover. Order a municipal lien search before closing. The title commitment doesn't always catch it.
2
26
An $80,000 house can cost $140,000 to rebuild. The policy prices off the $140,000. Most people budget insurance as a percentage of purchase price and find that out at renewal. Quote it during the inspection period, off the rebuild number.
1
2
44
The related one is the roof. No carrier writes past about twenty years. The fix is a roof certification, a licensed roofer signing off on three to five years of remaining life, a couple hundred dollars. Without it you are not getting a quote at all.
2
25
A 3BR that becomes a 4BR usually picks up more rent than the room costs, because the payment standard moves per bedroom. Two things kill it. Egress on the window, and the 4BR utility allowance comes straight back out of your number. Most price only the framing.
1
2
43
The order matters. Pull the PHA's current payment standard and allowance schedule before you frame anything, then have the inspector confirm the room counts. A room that fails egress is a den on the next inspection.
1
24
Three weeks of hard money carry on a $250,000 loan is about $2,300. That is what an unset electric meter costs while you wait on the utility. The electrician can file the service application the day he quotes it. Most file it the day they start.
1
1
3
54
Ask him to send you the application confirmation. Then call the utility's service desk yourself for the current reconnect window in that township. Both of those happen before a single wire gets pulled.
2
18
Two numbers on the same house. A contractor walks it and says about $90,000. A dated bid on letterhead with the scope attached says $106,000. The lender funds off the second one. So does the seller when you ask for a credit.
1
1
4
77
A bid is dated the day the sub signs it and most hold thirty days. Past that he reprices material and you're back to a conversation. If you want to argue a credit with it, it has to land inside the inspection period.
3
25
$120,000 rehab budget on a Nashville house. Two kitchens, two baths, no square footage added. Roof and exterior $16,000. PEX repipe and water heater $11,000. Windows and three doors $10,000. Electrical $8,000. The subfloor repair sits inside the kitchen line.
3
1
3
64
That budget is also a draw schedule. The lender funds lines in arrears, so demo, the roof and the repipe come out of pocket before the first inspection. Group the early trades so you can call one line complete and get the inspector out sooner.
1
23
Saw a house posted this morning. $80,000 to buy, $1,000 a month. That reads like a 15% cap. Take out taxes, insurance, 10% to a manager, a month empty and $1,500 of repairs. You're at seven. Seven still works. Underwrite it there and nothing surprises you.
1
1
2
61
The line people leave out is the turn. Repairs trickle, a turn is a lump: clean, paint, patch, re-key, a few weeks empty. One every other year on a $1,000 house takes another point off that seven. Ask a manager how long his last three vacancies sat.