I'm Jeramy, founder of Volterra Advisors. If you own land or a building and wonder whether it could host a data center, that's exactly what we figure out: power, zoning, fiber, and real value. I post about sites, power, and the data center buildout. Questions welcome, my DMs are open. volterraadvisors.com
Site wanted: 300 MW energized by June 30, 2027. We're working with a premier AI lab with a mandate from its leadership; they bring their own modular units and can close quickly. One site, zoned and entitled. US or Canada, lease or buy.
volterraadvisors.com/call-fo…
1
2
84
Loudoun County, home of Data Center Alley, has paused review of data center and substation applications for up to 12 months, counted from Sept. 15. 33 are already in line, and staff expect a backlog after.
If your land there needs board approval, plan for the wait.
1
1
102
Minneapolis voted 7-6 to limit new data centers to existing buildings in two downtown zoning districts, each needing council approval. A mayoral veto is still possible.
If it holds, owners of underused downtown buildings have a path, with a council vote on every project.
45
Worth repeating: a queue position is not an energization date.
Ask the utility which studies are still open, which upgrades are on you, and what happens if a project ahead of you drops out.
Those answers move your schedule more than the number does.
38
Jeramy Utara | Volterra Advisors retweeted
Converting a vacant industrial building into a data center only pays if reuse beats new construction once you count structure, power, cooling and approvals. Our founder in the Baltimore Business Journal: bizjournals.com/baltimore/ne…
An empty warehouse isn't automatically a head start for a data center. What the building used to draw and what the utility can deliver next are two different numbers. My piece in the Philadelphia Business Journal on testing a conversion: bizjournals.com/philadelphia…
39
A substation down the road is a reason to look, not proof a site can get power. I wrote for the Baltimore Business Journal on five questions to answer before pricing land for a data center: bizjournals.com/baltimore/ne…
1
85
Minneapolis just voted 7-6 to limit new data centers to existing buildings in two downtown zones, each needing council approval, and the mayor may veto. For owners of underused downtown buildings, a data center use is on the table. Expect a public vote on every one.
27
Brewer, Maine is moving to allow 50 MW data centers in some industrial zones, up from 20 MW, while nearby Bangor and Old Town banned them this year. Neighboring towns are splitting. If you own industrial land, which side of the town line it sits on can matter more than acreage.
33
Oregon regulators just approved a Pacific Power tariff: new data centers using 20 MW+ get their own customer class, sign long-term contracts and pay the full cost of their service, starting Jan 1. Paying your own way is becoming the norm. Ask buyers if they've budgeted for it.
18
Seven residents are suing McCormick County, SC over a 678-acre rezoning for a data center, alleging notice and procedure failures. A yes vote isn't the finish line. If your land is being rezoned, make sure every step is clean, or the approval can be challenged later.
35
A permitting bill in Congress would speed reviews for transmission lines and gas pipelines, but charge data centers extra for grid access. Faster power, bigger bill. If a buyer's numbers assume today's power costs, ask what happens to the deal if this passes.
24
San Francisco's planners say the city's grid is near capacity even before new data centers, and supervisors vote Tuesday on extending a citywide pause another 10½ months. When the grid is full, housing and data centers compete for the same megawatts. Know where your site stands.
12
A substation down the road is a reason to look, not proof a site can get power. In the Baltimore Business Journal, I walk through five questions to answer before putting a price on land for a data center: bizjournals.com/baltimore/ne…
25
Thinking about selling or leasing land for a data center? Before the first call, pull together:
- anything the utility has put in writing
- zoning and permitted use
- fiber, water, access, usable acres
- your goal: sale, option or ground lease
The first call goes further.
59
Jeramy Utara | Volterra Advisors retweeted
🚨 A man who lives LESS THAN HALF A MILE from Google's data center in Clarksville, Tennessee, says noise and light pollution have NOT been an issue.
"Everybody's saying how bad they're gonna be... I haven't seen anything negative. I've only seen the positive side.”
Oklahoma City just extended its pause on data centers over 75 MW through 2027. Nearby Edmond paused all of them until next June, with no developer even asking yet. For landowners, a moratorium is a clock. Check whether your town has one, and how long it runs, before you sign.
1
62
A new modular data center product plugs in behind existing commercial meters and uses spare capacity already on site: 1 to 20 MW in 12 to 16 weeks, per the company. If your building has heavy electrical service you're not using, find out how much. That number has value now.
2
3
158