Photo by PNG Power Ltd (@PNGPowerLtd)Photo by PNG Power Ltd (@PNGPowerLtd)Photo by PNG Power Ltd (@PNGPowerLtd)Photo by PNG Power Ltd (@PNGPowerLtd)Photo by PNG Power Ltd (@PNGPowerLtd)Photo by PNG Power Ltd (@PNGPowerLtd)Photo by PNG Power Ltd (@PNGPowerLtd)Photo by PNG Power Ltd (@PNGPowerLtd)Photo by PNG Power Ltd (@PNGPowerLtd)Photo by PNG Power Ltd (@PNGPowerLtd)
Easipay System Outage Wednesday, January 24, 2024
102
PRESS STATEMENT Kerema & Maprik get new Gen Sets!
100
POM Kilakila Feeder 2 - Customers on Kilakila Feeder 2 - multiple faults experienced on the feeder which is affecting power supply to Vabukori, Gabutu, Sabama, Kaugere, Badili, Pari and Kilakila. Our teams are working on site now and we anticipate to have power up by 8pm.
74
ROUNA 1 REHABILITATION AND UPGRADING WORKS TO BEGIN PNG Power advises its valued customers and the general public in Port Moresby that it will be undertaking important maintenance work under the Rouna 1 Rehabilitation Project this weekend.
1
79
PNG POWER COMMENCES METER BOXING EXERCISE TO COMBAT POWER THEFT IN PORT MORESBY Today, PNG Power Ltd commenced the Meter Boxing project in Port Moresby to combat power theft. pngpower.com.pg/index.php/ne…
50
Mass Disconnection Exercise
3
3
244
Planned Shutdown for the Rouna 2 water intake screen cleaning
1
151
Waigani Substation Planned Outage on Sunday January 22, 2023
1
1
1
1
211
PORT MORESBY POWER SUPPLY FULLY RESTORED All feeders restored. System back to normal. If you are still experiencing an outage within your area, please do not hesitate to get in touch with our Call Centre team. Toll Free 116, [email protected]. WhatsApp: 70001009.
1
1
2
267
PORT MORESBY POWER SUPPLY Update 1 Following feeders have been restored so far. Bomana 1 & 3, Kanudi 2 & 3, Boroko 1, 2, 3, 5, 6 & 7, Konedobu 3 & 5 and Waigani 2. Restoration work still ongoing for the other feeders.We will keep you posted regarding this.
1
1
125
PORT MORESBY TOTAL POWER OUTAGE PNG Power advises its customers and the general public in Port Moresby and surrounding areas in Central Province that there was a total power outage experienced at 8.32 am. Our teams are now working on the power restoration process. Updates soon.
3
136
PNG Power is now on WhatsApp. You can message your power issues to 70001009 and get real time feedback with a ticket number. This service is for messaging only.
1
2
1
6
508
Apologies for the delay in restoration. During a system outage, we have to start up a standby genset at our Rouna 2 power station. Attempted start-up failed at 5.30pm. Issues has been rectified. Restoration is going ahead. More updates on facebook.com/PNGPowerLtd
2
10
PORT MORESBY SYSTEM OUTAGE 8.20pm Broken Line insulator on Transmission Line between Konedobu and Kanudi substation. The fault located at Hohola. Our teams are now working on restoration. Detailed updates on facebook.com/PNGPowerLtd
1
3
PORT MORESBY POWER UPDATE 5 Boroko Feeder 8 restored. Waigani Feeder 3 restored. Feeders yet to be restored are Boroko 2,3,4,5,6 and 7. Restoration progressing. Dial 116 for more information, email [email protected] or message us on Facebook.
1
1
PORT MORESBY POWER UPDATE 4 Konedobu Feeders 3, 4 and 7 restored. Waigani Feeders 3, 4 and 5 restored. Boroko 1 restored. Feeders yet to be restored are Boroko 2,3,4,5,6,7 and 8. Restoration progressing. Dial 116 for more information, email [email protected].
1
2