Replying to @Ticktok08 @sholard_mancity
See FIDIC Plant and Design-Build (2017), Clause 15.6(b). Contractors are businesses that commit substantial resources to securing contracts, especially where termination is after mobilisation. These commitments matter when assessing termination compensation.
1
1
29
Replying to @muriaso
China Exim Bank committed to finance the project, subject to a Chinese contractor being awarded the contract—hence the restricted procurement. But a financing commitment isn't a signed financing agreement; there’s a process in between. Research project financing further.
13
The @ppp_kenya has terminated a PIP by Elevolution Engenharia, S.A., Portugal for the Financing, Design, Construction, Operation and Transfer of the Thuci Dam Project under the PPP framework & directed @MOWSI_KE @Irrigation_Auth to consider an alternative procurement route.
2
79
Even with a competent Employer’s Contract Administrator, if the Site Agent doesn’t understand contract administration, you've a recipe for chaos.
These are the people making daily decisions on site. Contract administration shouldn’t be an afterthought in engineering education.
🤖 Made with AI
Kenya’s engineering curriculum is overly technical,often at the expense of vital supporting courses: business communication,project economics,commercial management & contract administration.
I’d bet 80% of fresh engineering graduates leave university without a clue what FIDIC is.
🤖 Made with AI
Replying to @GE_Albert5
Cost adjustment clause. E.g in FIDIC Conditions of Contract for Plant and Design-Build, Second Edition 2017 (Yellow Book), Clause 13.7
At an estimated cost of KSh 38.841 billion, China Communications Construction Company (CCCC) will design, construct & finance the Athi Dam & Associated Irrigation Water Conveyance System along the Galana River to supply irrigation water to the Galana-Kulalu Food Security Project.
Under FIDIC, contracts are categorized into 8 types(called books)-broadly refered to as "FIDIC Rainbow Suite".
These books rep. std contracts designed to cover different project delivery methods,each book targeting a specific risk allocation, design responsibility,& project type.
FIDIC—Fédération Internationale Des Ingénieurs-Conseils, the International Federation of Consulting Engineers. Founded in 1913, develops standard contract forms and promotes best practices to ensure fairness, quality, and transparency in infrastructure projects globally.
Dear Mjengo X,
For the next couple of months, I’ll be breaking down FIDIC frameworks and contract/business modes to simplify construction contract management for professionals and the general public. Let’s demystify the standards that shape our projects. Retweet widely.
"It's either you involve professionals in design and implementation of your project; or you will involve them to remedy the mess. The latter is very expensive" Eng. @cenas_j told me this.