🚧 South Street Project Update: PAVING IS COMPLETE! 🎉
This is the update we’ve been waiting for! The new asphalt surface is officially complete on South Street Phase I, and after months of construction, the project is very nearly finished.
From a new water main and service lines, to stormwater improvements, subgrade stabilization, new curbs, sidewalks, driveway approaches, yard restoration, and now a brand-new road surface, South Street has undergone a complete transformation.
At this point, only one major piece remains: installation of the new street lighting! 💡
A huge thank you goes out to the South Street residents for their patience and cooperation throughout construction. We know living in the middle of a major reconstruction project isn’t always easy, but we hope everyone agrees that the finished product is looking pretty great.
Phase I is almost in the books! 🏁
109
🚧 South Street Project Update: The End Is Near! 🚧
This is a BIG one! All concrete work on the South Street Reconstruction Project is officially complete! 🎉 Yard grading behind the new sidewalks has also been completed, and grass will be planted tomorrow, Saturday, September 26th.
Next week brings one of the final major stages of the project. Wagner Paving will be on South Street Monday and Tuesday to fine-grade the road surface in preparation for asphalt paving later in the week. Residents in the project area will need to have their vehicles out of their driveways by Monday morning so crews can complete this work and prepare for paving.
Once asphalt work begins, paving will take a minimum of two days, with at least one day for the base course and another for the surface course. The good news is that the road will be drivable shortly after the asphalt is placed, so access should return relatively quickly as each phase is completed.
After paving, only one major piece remains: the new street lights!
After months of water mains, storm sewer, dirt, concrete, rain delays, curbs, sidewalks, grading, and a whole lot of patience... THE END IS NEAR! 🏁
Thank you to our South Street residents and everyone in the community for your patience and cooperation throughout this project. We are excited to see the new South Street coming together!
2
1
99
🚧 South Street Project Update 🚧
We are getting close!
Concrete work on South Street is nearly finished, with only one more pour remaining. Next week, crews are expected to finish the remaining concrete work, begin grading yards behind the new sidewalks, and start final grading of the road in preparation for asphalt the following week.
The continued rain has slowed things down a bit, but the project is definitely in the home stretch. The curbs, sidewalks, and approaches are really starting to bring the street back together, and the finish line is in sight!
Thank you again to South Street residents and everyone traveling through the area for your continued patience and cooperation as we work through these final stages of the project.
1
114
🚧 South Street Project Update 🚧
The finish line is starting to come into view on the South Street Reconstruction Project!
Concrete curbs have now been installed, and sidewalk and driveway approach work is underway. This is an exciting step, as the project is really beginning to look like a finished street again.
We expect the remaining concrete work to take a couple of weeks before crews move on to preparing the road for asphalt. As always, the schedule may shift some depending on weather and construction conditions, but great progress is being made.
Thank you again to South Street residents and everyone traveling through the area for your continued patience and cooperation. We know construction can be inconvenient, but these improvements will make a big difference for the long-term future of South Street!
96
🚧 South Street Project Update — Curb Work 🚧
Concrete curbs are scheduled to be poured tomorrow, Thursday, September 3rd, beginning very early in the morning.
We ask that residents who live on South Street within the project area please move their vehicles tonight where possible.
Once string lines are set up and curb work begins, residents will not be able to enter or exit driveways in the active work area. Moving vehicles ahead of time will help ensure residents have access to transportation while the concrete work is underway.
Thank you for your patience and cooperation as this important phase of the project moves forward!
107
🚧 South Street Project Update 🚧
Another big step forward on the South Street Reconstruction Project: subgrade stabilization is complete!
Curb work is scheduled to begin on Thursday, September 3rd, and continue into Friday. Sidewalk work is expected to begin next week.
Our contractor has dropped off notices to South Street residents regarding the upcoming curb work and parking restrictions. Please note that some of the notices included the wrong date. The correct start date for curb work is Thursday, September 3rd.
Driveways will be inaccessible while curb work is being completed and for a period of time after the curbs are poured. Residents are asked not to park on the road beginning Thursday morning so concrete crews have the room needed to work safely and efficiently.
We appreciate everyone’s patience and cooperation as the project continues to move forward!
78
🚧 South Street Project Update 🚧
Despite the rain over the last couple of weeks, progress continues on the South Street Reconstruction Project!
The stormwater work is now complete, marking another major underground infrastructure milestone for the project. Road base stabilization has also begun and will continue into next week.
Once the base work is completed, crews will move on to grading the road in preparation for curb work in the coming weeks. Step by step, South Street is continuing to take shape!
Thank you again to residents for your continued patience and cooperation as this important project moves forward.
86
🚧 South Street Project Update 🚧
You may have noticed it rained in Botkins this week. Just a little. Maybe once or twice. Or constantly.
Due to the rain, progress on the South Street Reconstruction Project was delayed this week. Crews were still able to complete some stormwater work, and the stormwater portion of the project is now nearing completion.
With better weather expected next week, crews will have the opportunity to begin road grading and subgrade stabilization. This work helps prepare and strengthen the base of the road before the new road surface is installed.
We appreciate everyone’s continued patience and cooperation as the project keeps moving forward!
1
104
🚧 South Street Project Update 🚧
Progress continues on the South Street Reconstruction Project!
The stormwater main replacement work is nearing completion, marking another important step forward in the project. This underground work is a key part of improving drainage and supporting the long-term reliability of the street infrastructure.
Next week, crews are expected to begin subgrade stabilization and road surface grading. In plain terms, this means preparing and strengthening the road base so it is ready for the new road surface later in the project.
We continue to thank residents for their patience and cooperation as work moves forward. Please continue to use alternate routes when available, and as always, contact the Village Office with any questions.
1
172
🚧 South Street Project Update 🚧
Progress continues on the South Street Reconstruction Project!
The new water main has passed all required testing, and all water service lines have now been connected. This marks a major milestone for the project and completes the water portion of the underground infrastructure work.
While crews were waiting on final water line testing, some excavation work for future sidewalks also began. Now that the water main work is complete, crews have started the next major phase of the project: replacing the stormwater main.
We appreciate everyone’s continued patience and cooperation as this important project keeps moving forward!
120
🚧 South Street Reconstruction Phase I Update 🚧
This week on East South Street has been all about the new water main!
Crews have been working on replacing the existing water main with a larger, upgraded main that will help improve water service for residents in the project area. This is a major underground improvement that will strengthen the Village’s water infrastructure, improve reliability, and better support long-term service needs along South Street.
Once the new main is fully installed, tested, and placed into service, new service lines will be connected for residents served by the upgraded main.
We continue to thank everyone for their patience and cooperation throughout this project. As always, if you have any questions, please do not hesitate to give the Village Office a call.
1
402
🏓🎉 THE WAIT IS OVER—PICKLEBALL IS HERE! 🎉🏓
The four brand-new pickleball courts at Botkins Community Park are officially OPEN and ready for play! The tennis court also received a fresh new paint job and is looking better than ever. 🎾
This is an exciting addition to our community, and we cannot wait to see residents of all ages out enjoying the courts!
A huge thank-you to the Botkins Joint Recreation Board and to the incredible legacy of Louise Sheets, whose generosity continues to make lasting improvements like this possible throughout Botkins.
Grab your paddles, call your friends, and head to the park—it’s time to play! 🏓
4
270
Happy Independence Day from the Village of Botkins!
Today, as we celebrate the 4th of July, we also mark a truly historic milestone: America’s 250th birthday. For two and a half centuries, our nation has been shaped by the ideals of freedom, opportunity, service, and community.
Here in Botkins, we are proud to be part of that American story. Whether you are spending the day with family, attending a cookout, watching fireworks, or simply enjoying time with friends and neighbors, we hope your holiday is safe, meaningful, and full of gratitude.
From all of us at the Village of Botkins, Happy 250th Birthday, America!
🤖 Made with AI
1
87
🚧 South Street Reconstruction Project – Phase I Begins July 6 🚧
The South Street Reconstruction Project Phase I is here! Work is scheduled to officially begin on Monday, July 6.
This is an exciting and significant infrastructure project for the Village of Botkins. Phase I will include the replacement and upgrade of the water main and stormwater main, installation of new sidewalks, curbs, and street lights, and a full replacement of the roadway from the base up through the surface course.
Phase I includes the portion of East South Street from Robinhood Lane to First Street.
Residents who do not live on South Street are encouraged to use alternate routes when available throughout the project. Residents directly impacted by the project who have any questions should not hesitate to contact Village Administrator Randy Purdy at 937-210-6265 at any time.
We appreciate everyone’s patience and cooperation as this important project moves forward. Phase II of the South Street Reconstruction Project is scheduled to begin next year.
1
2
244
Today, the Village of Botkins proudly dedicated Cole Field Park, ensuring this cherished community gathering place will be preserved and enjoyed by residents for generations to come.
This project would not have been possible without the partnership, generosity, and vision of so many people who care deeply about our community. We extend our sincere thanks to the Botkins Beautification Club, Botkins Youth Baseball & Softball, Botkins Community Club, and the lasting legacy of Louise Sheets for helping improve Cole Field Park and cement its place as a cornerstone of recreation, fellowship, and community pride in Botkins.
A special thank you to everyone who attended today's dedication and to all who have supported this project along the way. We look forward to seeing families, athletes, and residents continue to make memories here for many years to come.
Cole Field Park is more than a park—it's a lasting investment in the future of our community. ⚾🏞️💛🖤
Did you know you can receive Village updates by text message?
The Village uses text notifications to send important non-emergency messages to residents.
These notices may include updates about:
🗑️ Trash delays
🚧 Village project updates
🧹 Street sweeping
🌿 Limb, brush, and leaf pickup
To sign up, please send your cell phone number along with your service address, and the information will be added to your utility account so you can receive notifications.
Residents may also update this information by creating or logging into their utility account through the link on the Botkins website homepage:
botkinsohio.com
Please send updated information to:
[email protected]
98
Hageman Woods Subdivision Phase II Update
The road for Hageman Woods Estates Phase II has officially been paved!
We are excited to see continued progress and look forward to welcoming more high-quality single-family homes to our community. This project represents another positive step in Botkins’ continued growth while preserving the strong neighborhood character that makes our village a great place to call home.
Stay tuned for more updates as development continues!
1
97
Today, the Village of Botkins pauses to remember and honor the brave men and women who gave their lives in service to our nation.
Their sacrifice protects the freedoms we enjoy each day, and we are forever grateful to them and to the families who carry their memory forward.
As we gather with family, friends, and neighbors this Memorial Day, may we do so with gratitude, humility, and remembrance.
We remember. We honor. We are grateful.
🚧 Big news for Botkins! 🚧
The Village of Botkins is excited to announce that we have secured funding through the Ohio Public Works Commission for Phase 2 of the South Street Reconstruction Project!
This is a major win for our community. While Phase 1 is set to begin in the coming weeks, this funding will allow Phase 2 to be completed next year, in 2027. Even better, this funding will drastically offset the cost of the project for the Village and our residents. 👏
We are thrilled to keep this important project moving forward and continue investing in Botkins’ infrastructure.
Keep an eye out for future updates on South Street Phase 1 in the coming weeks! 🚜